GENERAL & WIRING NOTES:
ALL ELECTRICAL WORKS PERTAINING TO WIRING OF ELECTRICAL SYSTEMS SHALL STRICTLY CONFORM TO IEE LATEST EDITION OF RULES & REGULATIONS.
ALL WIRING SHALL BE DONE IN PVC CONDUIT TO BE CONCEALED IN WALLS, SLABS, COLUMNS & FLOOR OR AS SHOWN ON DRAWINGS. OR AS SHOWN ON DRAWINGS.
THE WIRING SHOULD BE STARTED ONLY AFTER THE CONDUIT SYSTEM HAS BEEN COMPLETED AND ALL OUTLET BOXES ARE FIXED AT THEIR RESPECTIVE POSITIONS.
ALL PVC CONDUITS SHALL BE OF 3/4″ OR 1″ DIA, (DEPENDING UPON NUMBER OF WIRES) FROM SWITCH BOARD TO LIGHT POINTS AND 1″ D1A FROM DBs TO SWITCH BOARDS & POWER SOCKETS OR AS SHOWN ON DRAWINGS.
LIGHT / FAN POINT CONTROLLED BY ONE WAY SWITCH. WIRED WITH 1.5mmsq (3/0.029″) (AS OF WIRE) 2×2.5mmsq (7/0.029″) AS COMMEN NEUTRAL(N) & EARTH(E) WIRE.
LIGHTING CIRCUITS FROM RESPECTIVE DB TO SWITCH SOCKET WIRED WITH 3×2.5mm sq (7/0.029″) AS P+N+E
SOCKETS WIRED IN PARALLEL WITH 2×2.5mm sq AS P+N+E
POWER SOCKETS WIRED WITH 3x4mmSq AS P+N+E
WIRING FOR S.A/C 1-1.5 TON WIRED WITH 3x4mmSq AS P+N+E
WIRING FOR S.A/C 2- 2.5 TON WIRED WITH 3x6mmSq AS P+N+E
NO LUBRICATION EXCEPT AS RECOMMENDED BY MANUFACTURER SHALL BE USED FOR PULLING OF WIRES IN PVC CONDUITS. NO OIL OF ANY KIND SHALL BE USED.
COLOUR CODING FOR WIRING SHALL BE AS FOLLOWS: RED, YELLOW AND BLUE FOR PHASES, BLACK FOR NEUTRAL AND GREEN / YELLOW FOR CPC (EARTH).
THE NUMBER OF WIRES TO BE PULLED IN ANY CONDUIT FOR WIRING PURPOSES SHALL CONFORM TO IEE. TABLE
1″ DIA PVC CONDUIT SHALL BE USED FOR WIRING OF ALL OTHER SYSTEMS UNLESS OTHERWISE MENTIONED ON DRAWINGS OR AS SPECIFIED IN BOQ.
ELECTRICAL CONTRACTOR TO CONSULT ELECTRICAL CONSULTANT/ ENGINEER FOR ANY FURTHER CLARIFICATIONS. NO ASSUMPTIONS SHOULD BE MADE.
Electrical wiring and Circuits for building is also available in this link
For Download the Layout Plan click the Below link
Download CAD Layout for Building and Conduit Layout visit the link Technicalfiles.org
Building Wiring Test
1: Short Circuit Test
2: Open Circuit Test
3: Earth Leakage Test